Redevelopment of Neefestraße
Replacement construction of the bridges over the Im Neefepark road has been completed
The main construction work for the overall Neefestraße project has been completed. Trees are now being planted in the centre and edge areas.
The Neefestraße project as a whole was realised in detail from July 2023 to November 2024:
- Replacement construction of the two Neefestraße bridges over the Im Neefepark road.
- Extension of the threading lane from Neefepark onto Neefestraße towards the city centre by 75 metres by building a 100-metre-long retaining wall
- Road resurfacing of Neefestraße between the A72 and Südring in both directions over a total length of 1,200 metres. Noise-reducing asphalt was used in the process.
This important and heavily used traffic infrastructure has thus been upgraded.
The lengthening of the threading lane has improved road safety at the accident blackspot.
The costs totalled around 11.6 million euros. The Free State of Saxony subsidised the project with around 5.7 million euros, as it was a measure in the special interest of the state.