Special inspection of the Fabrikweg bridge in Einsiedel
Short-term closure required on 25 September
On Wednesday, 25 September, from 8 am to approx. 4 pm, a special bridge inspection will be carried out on the Fabrikweg bridge over the Zwönitz in Einsiedel.
For this purpose, the decking planks will be removed at selected points and the underlying material will be inspected, in particular for moisture ingress.
During this time, it will not be possible to walk on or cross the bridge.
Unfortunately, detours via Einsiedler Hauptstraße and Einsiedler Neue Straße cannot be avoided.