Provision of funds for the new Fantasia daycare centre
At its meeting today, Chemnitz City Council approved the provision of unavoidable additional funds for the construction of the new Fantasia daycare centre in Altendorf in 2019/2020.
The construction project was scheduled to cost around 4.9 million euros, of which 548,000 euros in subsidies for the remediation of contaminated sites were planned.
The result of the tender and lower payments from subsidies resulted in an additional requirement totalling 790,000 euros, meaning that the daycare centre construction project now requires a total financial requirement of just under 5.7 million euros.
The continuation and completion of the construction project in 2020 is secured with the provision of a commitment authorisation.