Mobile classroom GS Altendorf

Delivery of the modules started today

Delivery of the modules for the mobile classrooms at Altendorf Primary School began today, 15 November 2016. This should be completed by 30 November 2016.

Once delivery and assembly have been completed, the installation of the modules will begin, which will take around four to five weeks. Depending on the weather conditions, the yard paving will be adjusted and completed after approximately one to two weeks.

After the final assembly work, which will take around one to two weeks, and the building inspectorate approvals by all test engineers, which will also take around one to two weeks, the move, including furnishing, panel assembly and final cleaning, is scheduled for the February holidays from 13 to 25 February 2017.

Lessons in the mobile classrooms are planned for after the February 2017 holidays.