Liddy-Ebersberger-Straße football pitch to be extended

A new streetball court, a table tennis table and two graffiti walls are being built in Gablenz

The public play and leisure centre on Liddy-Ebersberger-Straße is to be extended. By the end of November, a streetball pitch and a table tennis table will be built next to the existing football pitch. In addition, two graffiti walls will be erected in the newly designed area as well as two benches and a litter bin.

Construction is scheduled to start on 28 October 2019. The construction work should be largely completed by 29 November 2019. Remaining landscaping work should be completed by 27 March 2020.

The facility was planned by JACOB + BILZ Landschaftsarchitekten. The costs for planning, construction and planting services as well as the production and installation of the play equipment totalled approx. 52,000 euros.