Further school construction work begins in the autumn holidays
During the autumn holidays, further projects from the special school building construction programme will be implemented. The measures that will begin in the autumn holidays include
Vocational School Centre for Business II: Fire protection measures and construction of a second structural escape route - 376,000 euros will be invested, of which a good 150,000 euros are subsidies.
Heinrich Heine Primary School: Façade renovation, replacement of windows and construction of barrier-free access (lift) to the school building as well as general refurbishment of the sports hall - 2.5 million euros will be invested, of which just under 1 million euros are subsidies.
Reichenbrand primary and secondary school: Drying out, roof and façade renovation and interior work in parts of the school building and sports hall - 2.9 million euros will be invested, of which just under 1.2 million euros is subsidised.
Sonnenberg primary school: Roof and façade renovation as well as drainage of the school building and exterior and interior renovation of the sports hall - around 2.74 million euros will be invested, of which a good 1 million euros is subsidised.
Georg-Weerth-Oberschule: Roof and façade renovation, renovation of the toilets and heating system, fire protection measures, renovation of the lightning protection system and electrical installation work in the school building - around 2.5 million euros will be invested, of which just under 1 million is subsidised.
Altendorf primary and secondary school: interior refurbishment, renewal of building services and fire protection measures including external staircase - around 1.25 million euros will be invested, of which just under 500,000 euros is subsidised.
"Johann-Heinrich-Pestalozzi" learning support centre: Partial renovation (roof and façade renovation, drainage, work on fire protection, heating, ventilation, plumbing, electricity) - almost 2 million euros will be invested, of which around 900,000 euros are subsidies.
Gablenz primary school sports hall: renovation of the roof and façade as well as the changing rooms and sanitary facilities - 700,000 euros will be invested, of which around 280,000 euros will be subsidised.
The city of Chemnitz is not yet able to give an exact date for the start of construction. The companies have a deadline of 14 working days to start work.
In principle, the aim is to minimise disruption to lessons by carrying out the noisy work early in the morning, during breaks or after lessons. Nevertheless, noise disruption to lessons during ongoing work cannot be completely ruled out, as most of the work has to be completed by the end of 2014.
Work began on ten buildings during the summer holidays and in September. In December, work will begin at Untere Luisen Secondary School and Josephinen Secondary School. In addition, relocations/removals within the properties or partial relocations will be carried out in the 4th quarter in preparation for the actual construction work. This is the case in the gymnasium of P. Neruda primary school, the gymnasium of Gablenz primary school, Altendorf secondary school, Baumgarten primary school Grüna, V. Tereschkowa primary school, Reichenbrand school and the J. H. Pestalozzi learning support centre.
The Rabenstein primary school will be the last project in the special programme to begin in spring 2014. An award procedure for the planning services was initially necessary here.