Current and planned major construction sites in Chemnitz

In the city of Chemnitz, major construction measures are necessary now and in the future in order to expand and maintain the infrastructure. Many of these are being implemented as coordinated measures by various stakeholders. This means that the infrastructure is being renewed and expanded on several levels at the same time, for example, the civil engineering department is renovating the road surface and pavements, CVAG is renewing tracks or expanding stops and Eins and ESC are laying new lines. In addition, there are construction projects by Deutsche Bahn (Chemnitzer Bahnbogen), the neighbouring districts and the State Office for Road Construction and Transport (LASuV).

The necessary construction measures entail temporary cuts: diversions, closures and restrictions for road users as well as residents and businesses. The numerous construction sites are being coordinated by the City of Chemnitz's civil engineering department.

Priority measures in the main road network in 2021:

  • Annaberger Straße (coordinated construction project by DB, CVAG, ESC, eins/inetz and the Civil Engineering Office)
  • Augustusburger Straße (DB - Chemnitzer Bahnbogen)
  • Bahnhofstraße (coordinated construction project by CVAG and civil engineering office)
  • Bernsdorfer Straße (DB - Chemnitzer Bahnbogen)
  • Reichenhainer Straße (DB - Chemnitzer Bahnbogen)
  • Zschopauer Straße (DB - Chemnitzer Bahnbogen - and civil engineering office)

The following is an overview of current and planned major construction projects in Chemnitz:

Road

Area

Construction measure

Period

Annaberger Straße

between Erdmannsdorfer Straße and Krenkelstraße

Construction of the drinking water pipeline

since March until December 2021

Annaberger Straße

between Reichs- and Treffurthstraße

Track, road and pipeline construction (coordinated measure)

since the end of May until November 2022

Augustusburger Straße

between Martinstrasse and Dammstrasse

New construction of the railway overpass (Chemnitzer Bahnbogen)

since 2019 until 2022

Bahnhofstraße

at the level of Annaberger Straße

Renewal of the railway arches (CVAG)

from the end of October to December 2021

Barbarossastrasse

between Uhlichstraße and Weststraße

Construction of the drinking water pipeline

from March to November 2021

Bernsdorfer Straße

between Südbahnstraße and Turnstraße

New construction of the railway overpass (Chemnitzer Bahnbogen)

since 2019 until December 2021

Emilienstraße

between Agnesstraße and Straße der Nationen

Sewer construction (ESC)

from 2022

Erfenschlager Straße

between Albert-Junghans-Straße and Dr.-Karl-Wolff-Straße

Sewer construction crossings (ESC/eins/inetz) coordinated measure

from September to December 2021

Falkeplatz

between Theaterstraße and Bahnhofstraße

Repair of the track arches and
-covering (CVAG)

from the end of July to the end of August 2021

Frankenberger Straße

Mittweidaer Straße junction

Maintenance of the Brettmühle junction (LASuV)

in the 3rd quarter of 2021

Klaffenbacher Straße

at the level of Annaberger Straße

Replacement construction of a bridge

since March until the end of November 2022

Nevoigtstraße

between Unritzstraße and Uferweg

Sewer construction (ESC)

from August 2021 to October 2022

Küchwald - Wüstenbrand cycle path

from Kalkstraße to Rudolf-Krahl-Straße

New construction of the cycle path (1st construction phase)

from October 2021 to November 2022

Lugau - Wüstenbrand cycle path
(2nd section)

from Gewerbeallee Mittelbach to the Oberlungwitz town boundary

New construction of cycle path

March - December 2021

Reichenhainer Straße

between Görrestraße and Altchemnitzer Straße

New railway subway (DB)

since 2019 until 2022

Rosa-Luxemburg-Straße

between Bernsdorfer Straße and Zschopauer Straße

Sewer and road construction

from 2022-2023

Salzstraße

between Küchwaldstraße and Hechlerstraße

Sewer and road construction, incl. pavements

since March until October 2021

Schloßstraße

from Arndtstraße to Theunertstraße

Conversion to a cycle lane

since May until July 2021

Schulstraße

between H no. 82 and Erfenschlager Straße

Construction of the drinking water pipeline

from June to November 2021

Stollberger Straße

at the level of Paul-Bertz-Straße

Dismantling of the pedestrian tunnel

from September 2021

Stollberger Straße (Neukirchen)

at Zum Gewerbepark and Forststraße

Reconstruction of the junction area (municipality of Neukirchen)

n.n.

Street of Nations

at the level of Carolastrasse

Renewal of the points, track bends and landward stop (CVAG)

since the beginning of August 2020 until mid-August 2021

Straße der Nationen

between Wilhelm-Külz-Platz and Emilienstraße

Coordinated construction measure

since September 2020 until November 2021

Südring

between Paul-Bertz-Straße and Usti nad Labem street

Pavement rehabilitation of the landward carriageway

from mid-August to the beginning of September 2021

Trützschlerstrasse

between Georg-Weerth-Straße and Limbacher Straße

Construction of the drinking water pipeline

from April to July 2021

Ulmenstrasse

from Kappelbach to Heinrich-Beck-Straße

Sewer construction

from June to December 2021

Walter-Klippel-Straße

between Augustusburger and Eubaer Straße

Road construction (coordinated measure)

since February 2021 until July 2023

Wechselburger Straße

between Limbacher Straße and Waldenburger Straße

Sewer and pipeline construction

since March until September 2021

Weißer Weg

from Beutenbergstraße to Walter-Klippel-Straße

Roadway renovation

from August to October 2021

Zschopauer Straße

between Clara-Zetkin-Straße and Lutherstraße

New bridge construction, sewer construction (DB), road construction, coordinated measure

since 2019 until October 2021

Zschopauer Straße

from Bahnhofstraße to Moritzstraße

Expansion of the Bahnhofstraße junction area, track construction, media renewals, coordinated measure

since mid-May 2021 until the end of November 2022