Coordinated construction project Erdmannsdorfer Straße
From next Monday, 6 March 2017, until 22 December 2017, extensive construction work will be carried out to renovate the sewer and renew the drinking water pipeline, including road construction, in the area of Erdmannsdorfer Straße between Comenius Straße and the end of the street in Chemnitz.
The clients are the waste disposal company of the city of Chemnitz, the civil engineering department and eins energie. The construction section is approx. 450 metres long.
For this purpose, Erdmannsdorfer Straße must be fully closed in sections. An emergency lane will be created from Wolkensteiner Straße to the end of the road.
The total construction costs amount to approx. 690,000 euros. The company VSTR GmbH Rodewisch has been commissioned to carry out the construction work.